How much does commercial EV charging installation cost?

10 November 2026 · 6 min read · EV Smart

Why a price per bay does not exist, which elements actually drive the cost, and the routes that avoid a large capital outlay.

The short answer

There is no reliable price per bay for commercial EV charging. Anyone who quotes one before looking at your electricity supply is guessing. Two car parks with the same number of bays can differ by a factor of five, and the difference is almost always the connection, not the hardware.

What actually drives the number

The electrical connection. If your existing supply cannot carry the additional load, a new or upgraded connection becomes the largest line item and the longest task on the programme. This is why feasibility starts with capacity, not with chargers.

The equipment. AC workplace units are a modest cost per bay. DC rapid units are an entirely different order, particularly above 100kW, where the unit itself, the protection and often a dedicated substation all scale up.

Civil works. Foundations, ducting, containment, reinstatement, bay markings and lighting. Older car parks with no spare ducting cost more than new ones, and this is consistently the most underestimated element.

Installation and commissioning. Certified electrical work, testing and configuration. A charge point is a live electrical asset, not an appliance.

Software and payment. The management platform, card payment and roaming are usually ongoing costs rather than a one-off purchase.

Operation and maintenance. Monitoring, support, repairs and periodic inspection across the life of the asset.

The things that reduce cost

Load management is the most useful lever. Sharing the capacity you already have across several charge points often removes the need for a supply upgrade, because vehicles rarely all draw maximum power simultaneously.

Phasing is the second. Installing the containment and capacity now, and adding charge points as demand grows, spreads the cost without closing the option off later.

Grant funding is the third, but eligibility rules change and applications need to be made before the specification is fixed. Check the current position rather than relying on what applied two years ago.

Comparing quotations properly

A cheaper quotation is often not the same scope. Check whether the grid application is included, whether the civil works are provisional sums, who is responsible for maintenance after handover, and what happens at the end of the agreement. Whole-life cost is the only fair comparison.

If capital is the constraint, say so at the start. It changes which model gets assessed first, and it is a better conversation to have before a design is developed.

Next step

Tell us about your site.

Send us the location and what you are trying to achieve. We will come back with an honest view of what is possible, what it involves and what it is likely to cost.