What councils should consider when procuring EV charging infrastructure
20 October 2026 · 7 min read · EV Smart
A practical checklist for infrastructure officers: concession structure, accessibility, payment, reporting and the questions to ask before going to market.
Start with the outcome, not the equipment
Most council charging programmes begin with a target number of charge points. A more useful starting point is the outcome: residents without off-street parking able to charge near home, town centre visitors able to top up, or a depot fleet able to charge overnight. Each of those leads to a different specification, location list and commercial structure.
Decide who carries the capital and the risk
There are three broad routes: the authority funds and owns the assets; an operator funds and operates under a concession; or a mix, often supported by grant funding. Each produces a different risk profile, a different level of control and a different procurement exercise.
A concession does not remove accountability. It moves the operational burden to the operator, with the authority retaining obligations around performance, reporting and public money. Those obligations need to be written down and measurable.
Accessibility is a design requirement, not a retrofit
PAS 1899 gives guidance on accessible charging: bay dimensions, kerb heights, cable reach and the space needed to operate a charger from a wheelchair. Applying it at design stage is inexpensive. Retrofitting it after installation usually is not.
Payment has to work for people without a smartphone
Contactless card payment on public charge points removes the app dependency, which matters for accessibility and for visitors. If an app is also offered, it should be an addition, not the only route.
Ask what reporting you will actually receive
Availability, utilisation, energy delivered and fault response times should be reported on an agreed schedule, generated from the management platform rather than assembled by hand. Ask to see a sample report before award.
Test the failure scenario
Ask each bidder what happens when a charge point fails at 8pm on a Saturday. Who is called, how quickly, and how does the authority find out? A network that is installed but unmanaged becomes a complaint stream, and the reputational cost lands with the council.
Transitioning an existing network
If the authority already has charge points, an audit comes first: what is installed, what is still supported, what payment arrangements exist and what maintenance obligations are inherited. Migration is a project in its own right and should not be bundled into a new installation.